What an apartment renovation costs in Belgrade in 2026

Updated 2026-11-18 · RENOVA

A line that says “from €250/m²” and a line that says “turnkey €700/m²” are not the same product. These are tradesman labour rates for Belgrade and Novi Sad in autumn 2026, materials excluded.

Two quotes that should not be compared

A labour rate is hands and tools. Strip-out is €10–18/m², plaster €5–12, screed €8–14, skim and paint €5–9/m² of wall and ceiling, large-format tile €25–40, drywall €14–26, ceilings €12–22. A new electrical layout is €20–35/m², plumbing of a wet room €85–130/m². Cable, mix, paint, tile and fittings sit outside those bands.

A turnkey labour package of €250–400/m² is still labour: strip-out, services and finishes, priced on floor area. A company figure of €500–800/m² usually includes materials, coordination and margin. Do not add the two together.

Why the rows do not add up

Paint is priced on walls and ceilings, tile on its own surface, plumbing on the wet area rather than the whole flat. Adding every row and multiplying by the floor area doubles the real quantity.

  • A refresh, paint and floors, services left where they are: €30–55/m² of floor.
  • A kitchen without furniture, splashback and electrics: €50–90/m².
  • A bathroom with tanking and tile: €180–280/m² of wet area.
  • Turnkey labour for the flat: €250–400/m² of floor.

What moves a job inside the band

The low end is straight walls, little cutting and a clear plan of points. The high end is crooked geometry, moved risers, large-format tile with mitres, and a lot of boxing. The number to sign is the one after a site measure, not the one guessed from a photo.

A 55 m² example

Turnkey labour at the two ends is 55 × 250 = €13,750 and 55 × 400 = €22,000. That is not the tile, the cable or the paint. A 6 m² bathroom adds €1,080–1,680 of labour if it is not already inside the package. Materials on a flat of this size often match the labour if you buy mid-range porcelain and a proper electrical spec.

What does apartment renovation cost per m² in Belgrade in 2026?

Turnkey labour from a tradesman is €250–400/m² of floor, materials excluded. A company price with materials is more often €500–800/m².

Are materials included in the rate per m²?

No. A RENOVA rate is labour. Mix, cable, paint, tile and sanitaryware are priced apart.

Open the quote