A new-build flat ready for finishes: what has to happen before paint and floors

Updated 2026-11-18 · RENOVA

“Ready for finishes” in a Serbian new-build usually means bare walls and stubbed services, not a room you can put a sofa in. Paint and laminate come last, and they do not hide a bad screed.

What is often there, and what is not

Check the developer’s screed for hollows and level, the plaster for loose spots, whether the riser works, whether there is an earth, and whether the supply will take an electric hob. “The walls are white” does not mean they are ready for paint: it is often a primed base coat. If the geometry is out, plaster on guides at €5–12/m² is cheaper than a thick skim.

The order before the finishes

  • Partitions and wet points: shower, washer, board.
  • Electrics and plumbing while chasing is still possible.
  • Screed at €8–14/m², with a fall in the bathroom.
  • Plaster, then drywall boxes at €14–26/m².
  • Tanking and tile in the wet rooms.
  • Skim and paint at €5–9/m², the floor last.

Laminate laid before paint collects skim dust in the locks. Bathroom tile goes down before the final paint in the living rooms, so cutting dust does not land in fresh paint.

Floors and doors

Tie the screed height to the door leaves and the balcony threshold before the pour, not after. A door is hung once the floor level is known: labour €20–40/m² of opening, the leaf apart. A ceiling, if you need one, goes in before the walls are painted: €12–22/m² labour, the sheet and the lights apart.

Where this sits in a labour quote

A new-build with no old tile to lift is often cheaper than a second-hand flat on strip-out (€10–18/m² if you do have to strip). Turnkey labour of €250–400/m² of floor is still the guide when both services and finishes are in scope. “Paint it and lay laminate” is a refresh at €30–55/m², and it should not be called turnkey.